July 02 → July 04 2025

600 Block Pacific Ave | Prep Sidewalk, Curb, and Gutter, Pour Concrete

June 30 → July 02 2025

600 Block of Pacific Ave | Demo Asphalt, Curb, and Gutter

June 25 → June 27 2025

Pacific and Davis Intersection | Prep ADA Bump-Outs and Pour Concrete

June 23 → June 24 2025

Pacific and Davis Intersection | Demo Asphalt, Curb, and Gutter

June 09 → June 17 2025

600 Block Pacific Ave | S. Tomboy to S. Davis

Telluride Gravel will begin pouring the curb, gutter, and sidewalk along W. Pacific Ave. between S. Tomboy and S. Davis Streets. Intermittent closures will occur on W Pacific Ave during construction hours (8:00 am to 5:00 pm).

Intermittent closures will occur on the following days:

  • Monday, June 9
  • Tuesday, June 10
  • Friday, June 13

To address the closures, folks should expect the following detours:

  • Vehicular traffic will be rerouted via S Tomboy Street.
  • Pedestrian access will be rerouted either up Tomboy Street or onto the Telluride River Trail. 
  • The Galloping Goose Bus Stop at Carhenge will be moved to the corner of Pacific and Davis near Siam and Medicine Ranch.

We apologize for any inconvenience this may cause and appreciate your cooperation as we work on the Pacific Avenue Improvement Project. 

Want to sign up for Town of Telluride text notifications? Text TELLURIDE to 38276.

May 27 → June 13 2025

S. Tomboy St (Colorado to Pacific) | Curb, Gutter, and Street Paving

Preparation and Installation of curbs, gutters, and street pavement on S. Tomboy Street from Colorado to Pacific. 

May 27 → June 06 2025

W Pacific Ave (Tomboy to Davis) | Curb, Gutter, and Sidewalk

Preparation and installation of curb, gutter, and sidewalk along W Pacific Avenue from Tomboy to Davis. 

May 27 → May 30 2025

W. Pacific Ave (Mahoney to Davis) | Clearing and Grubbing

May 13 2025

Town Council Summer Construction Update

Public Works Director Kyle Beck provided an update surrounding summer construction projects at the Tuesday, May 13 Regular Meeting of Telluride Town Council.

May 05 2025

Construction Begins | Tomboy Street

Construction officially begins, starting with South Tomboy Street and prep work along Pacific Avenue.

May 01 2025

Pacific Avenue Improvement Project Public Information Session

Public engagement meeting held to share construction timeline and impacts with the community.

Click here to view the recording | Click here to review the presentation

March 2025

Project Goes to Bid, Funding Approved

Project goes out to bid. San Miguel County Fund approves additional funding support.

August 2024

Cost Estimates and Related Projects

Town continues refining plans and begins cost estimates for Mahoney Bridge and related projects.

March 12 2025

Town Council Overview Of The Public Works Department's 2024 Projects

Public Works presents updated sidewalk and streetscape concepts to Town Council.

Click here to view the recording.

August 2022

Town Council Review of Pacific Avenue Improvement Project (August 2022-August 2023)

Multiple Council work sessions and site walks held to finalize Pacific Avenue design details and coordinate goals for safety, access, and infrastructure.

July 2021

Southwest Area Conceptual Plan (SWAP) Adoption

Town Council adopts the Southwest Area Conceptual Plan (SWAP) as a roadmap for future improvements.

August 2020

Traffic Study

Traffic study completed to assess vehicle, bike, and pedestrian needs in the area.

June 2019

Community Engagement for Conceptual Planning

Community input collected through site walks, open houses, and public meetings (including Spanish-language outreach) June through October 2019.

May 2019

Conceptual Planning Begins

DHM Consultants hired to begin conceptual planning for the Southwest Area.