Town Park Oval & Warner Field Improvements

Share Town Park Oval & Warner Field Improvements on Facebook Share Town Park Oval & Warner Field Improvements on X (formerly Twitter) Share Town Park Oval & Warner Field Improvements on Linkedin Email Town Park Oval & Warner Field Improvements link

Phase 1 Construction Update

Phase 1 construction runs September 23 - December 18, 2026.

Phase 1 includes:

  • Warner Field outfield fence replacement and safety netting installation
  • Site drainage, including an underground drainage pipe across the north side of the Oval
  • Streetlight replacement and electrical infrastructure

What to expect: During construction, expect trail detours, construction noise, and construction traffic in the western portion of Town Park.

Access and detours, September 23 - early October:

  • Warner Field: Access Warner Field from the east via the pool pathway. The center-field gate near the parking lot is closed.
  • West and south Town Park: The west-side entrance from the Post Office bridge is detoured through early October. Use the east side of the Core Area to reach the western and southern portions of the park.

View the construction impacts map (September 23 - October 5), including work on the north side of the Oval, under Important Documents.

Phase 1 is separate from the Oval surfacing plan (Phase 2) and is moving forward as proposed and budgeted. Thank you for your patience while we work.

Project Overview

The Town of Telluride Parks & Recreation Department is making significant improvements to the Town Park Core Area, focusing on recreation, infrastructure, and public gathering space that serves residents and visitors year-round. This project is the third phase of the Core Area Improvements outlined in the 2020 Town Parks Master Plan, following completion of the Skatepark (2022) and the Warming Hut & Washstand (2025).

  • The Oval (Phase 2)
    • Site and perimeter improvements to support community gatherings, special events, and the winter ice rink.
    • Original design completed in 2021 and updated in 2025. Following the P&R Commission worksession, the design is being revised to reflect Alternate Concept #2 (grass oval with improved grading, drainage, and irrigation, and an expanded basketball court in its existing location).
    • Partial carryover from 2025 in terms of scope and budget allocation.
  • Phase 1: Warner Field, Site Drainage & Electrical
    • Warner Field outfield fence replacement and safety netting installation.
    • Site drainage, including an underground drainage pipe across the north side of the Oval.
    • Streetlight replacement and electrical infrastructure.
    • Full design completed in 2025.
    • Includes a new center-field gate to improve pedestrian circulation for special events and the general public.
    • Construction: September 23 - December 18, 2026.

Project Goals & Benefits

  • Oval Improvements
    • Support a wide range of existing uses: community gatherings, special events, informal activities, and the winter ice rink.
    • Improve site grading, drainage, and irrigation for the grass oval.
    • Expand basketball capacity at the existing court location to meet growing demand.
  • Phase 1 Improvements
    • Protects surrounding facility users during adult softball games.
    • Potentially opens Core Area availability on Monday, Wednesday, Friday & Sunday evenings and Saturday mornings/afternoons during adult softball season (mid-May through late July).
    • Includes a new center-field gate to improve flow exiting Town Park during large events.
    • Improves site drainage on the north side of the Oval.
    • Replaces streetlights and upgrades electrical infrastructure.

Project Planning

  • 2020: Town Parks Master Plan Update — Zehren & Associates
  • 2021: Core Area Improvements Design — Oval, Warming Hut, Skatepark, and vendor/festival staging; HARC Certificate of Appropriateness issued December 2021
  • 2022: Skatepark completed, Spring 2022
  • 2024–2025: Warming Hut & Washstand design/build; facility opened June 2025
  • 2025: Design verification and updates by CCA; community open house October 2025; HARC Certificate of Appropriateness issued September 2024; building permit issued December 2025
  • 2026: Town Council adopted 2026–2027 capital budgets; Phase 1 construction September 23 - December 18, 2026; P&R Commission worksession on Oval surfacing on July 29, 2026. Commission directed staff to develop Alternate Concept #2
  • 2027: Implement Town Park Core Area Improvements per P&R Commission direction, including:
    • Grass oval site enhancements (site grading, improved drainage, irrigation improvements, and sod replacement)
    • Expanded basketball facility at the existing location on the south side of the Oval

What's Next

  • Phase 1: Construction runs September 23 - December 18, 2026. Expect trail detours, noise, and construction traffic in the western portion of Town Park. See the Phase 1 Construction Update above for access and detours.
  • Phase 2: Staff and the design team are revising the Oval design to reflect Alternate Concept #2 for future P&R Commission review.
  • Budget: An updated Phase 2 cost estimate will be presented to Town Council during the budget process.
  • Phase 2 construction remains on hold pending completion of design review and budget approval.

Phase 1 Construction Update

Phase 1 construction runs September 23 - December 18, 2026.

Phase 1 includes:

  • Warner Field outfield fence replacement and safety netting installation
  • Site drainage, including an underground drainage pipe across the north side of the Oval
  • Streetlight replacement and electrical infrastructure

What to expect: During construction, expect trail detours, construction noise, and construction traffic in the western portion of Town Park.

Access and detours, September 23 - early October:

  • Warner Field: Access Warner Field from the east via the pool pathway. The center-field gate near the parking lot is closed.
  • West and south Town Park: The west-side entrance from the Post Office bridge is detoured through early October. Use the east side of the Core Area to reach the western and southern portions of the park.

View the construction impacts map (September 23 - October 5), including work on the north side of the Oval, under Important Documents.

Phase 1 is separate from the Oval surfacing plan (Phase 2) and is moving forward as proposed and budgeted. Thank you for your patience while we work.

Project Overview

The Town of Telluride Parks & Recreation Department is making significant improvements to the Town Park Core Area, focusing on recreation, infrastructure, and public gathering space that serves residents and visitors year-round. This project is the third phase of the Core Area Improvements outlined in the 2020 Town Parks Master Plan, following completion of the Skatepark (2022) and the Warming Hut & Washstand (2025).

  • The Oval (Phase 2)
    • Site and perimeter improvements to support community gatherings, special events, and the winter ice rink.
    • Original design completed in 2021 and updated in 2025. Following the P&R Commission worksession, the design is being revised to reflect Alternate Concept #2 (grass oval with improved grading, drainage, and irrigation, and an expanded basketball court in its existing location).
    • Partial carryover from 2025 in terms of scope and budget allocation.
  • Phase 1: Warner Field, Site Drainage & Electrical
    • Warner Field outfield fence replacement and safety netting installation.
    • Site drainage, including an underground drainage pipe across the north side of the Oval.
    • Streetlight replacement and electrical infrastructure.
    • Full design completed in 2025.
    • Includes a new center-field gate to improve pedestrian circulation for special events and the general public.
    • Construction: September 23 - December 18, 2026.

Project Goals & Benefits

  • Oval Improvements
    • Support a wide range of existing uses: community gatherings, special events, informal activities, and the winter ice rink.
    • Improve site grading, drainage, and irrigation for the grass oval.
    • Expand basketball capacity at the existing court location to meet growing demand.
  • Phase 1 Improvements
    • Protects surrounding facility users during adult softball games.
    • Potentially opens Core Area availability on Monday, Wednesday, Friday & Sunday evenings and Saturday mornings/afternoons during adult softball season (mid-May through late July).
    • Includes a new center-field gate to improve flow exiting Town Park during large events.
    • Improves site drainage on the north side of the Oval.
    • Replaces streetlights and upgrades electrical infrastructure.

Project Planning

  • 2020: Town Parks Master Plan Update — Zehren & Associates
  • 2021: Core Area Improvements Design — Oval, Warming Hut, Skatepark, and vendor/festival staging; HARC Certificate of Appropriateness issued December 2021
  • 2022: Skatepark completed, Spring 2022
  • 2024–2025: Warming Hut & Washstand design/build; facility opened June 2025
  • 2025: Design verification and updates by CCA; community open house October 2025; HARC Certificate of Appropriateness issued September 2024; building permit issued December 2025
  • 2026: Town Council adopted 2026–2027 capital budgets; Phase 1 construction September 23 - December 18, 2026; P&R Commission worksession on Oval surfacing on July 29, 2026. Commission directed staff to develop Alternate Concept #2
  • 2027: Implement Town Park Core Area Improvements per P&R Commission direction, including:
    • Grass oval site enhancements (site grading, improved drainage, irrigation improvements, and sod replacement)
    • Expanded basketball facility at the existing location on the south side of the Oval

What's Next

  • Phase 1: Construction runs September 23 - December 18, 2026. Expect trail detours, noise, and construction traffic in the western portion of Town Park. See the Phase 1 Construction Update above for access and detours.
  • Phase 2: Staff and the design team are revising the Oval design to reflect Alternate Concept #2 for future P&R Commission review.
  • Budget: An updated Phase 2 cost estimate will be presented to Town Council during the budget process.
  • Phase 2 construction remains on hold pending completion of design review and budget approval.
Page last updated: 22 Oct 2026, 11:00 AM