January 24 2025

Project Overview: Parklet and Business Impact Meeting

April 28 → May 09 2025

Mobilization (April 28 – May 2, 2025)

Before construction begins, the contractor will spend about a week mobilizing. This includes delivering equipment, setting up the work zone, marking utilities, and preparing for the removal of sidewalks and ramps.

May 08 2025

Project Information Session

Join us to learn about the project’s goals to improve intersections and sidewalks to meet ADA requirements. We’ll share the project timeline, explain how we’re working to reduce impacts on pedestrians and businesses, and answer any questions you may have.

May 12 → June 24 2025

Pine Street (May 5 – June 17, 2025)

Work officially begins at the intersection of Colorado and Pine Street. Crews will remove and replace concrete ramps, sidewalks, and curbs to bring this area into compliance with ADA standards. Traffic and pedestrian detours may be in place during this time.

May 30 → June 24 2025

Fir Street (May 23 – June 17, 2025)

While construction wraps up at Pine Street, crews will begin work at the Fir Street intersection. These two work areas will overlap slightly, with coordination in place to limit disruption to nearby businesses and foot traffic.

June 17 → July 07 2025

Spruce Mid-Block (June 10 – June 30, 2025)

Between Pine and Willow, a mid-block crossing near Spruce Street will be improved with updated ramps and sidewalk surfaces. Work here will occur while Fir Street is nearing completion.

June 27 → July 25 2025

Willow Street (June 20 – July 18, 2025)

Construction moves westward to Willow Street. This area will receive the same accessibility upgrades, and pedestrian detours will help maintain access to businesses.

July 18 → August 22 2025

Alder Street (July 11 – August 15, 2025)

Alder Street marks the last intersection in Phase I of the project. By this point, work on all intersections between Pine and Alder (except for mid-block Spruce) will be completed or nearly complete.

August 06 → August 29 2025

Aspen Street (July 30 – August 22, 2025)

Phase II begins at the eastern end of the project area with improvements to the Aspen Street intersection. Construction activity continues to be phased to limit closures to one intersection at a time.

August 26 → September 16 2025

Oak Street (August 19 – September 9, 2025)

The final intersection on the schedule is Oak Street. This portion will wrap up all major construction and accessibility improvements on Colorado Avenue.

September 17 → September 26 2025

Final Cleanup (September 10 – September 19, 2025)

Once all intersections are complete, crews will spend about a week cleaning up, removing equipment, completing any touch-up work, and restoring landscaping or pavement where needed.