Key Dates
Project Overview: Parklet and Business Impact Meeting
- Project Overview Meeting | Friday, January 24, 2025 | Click here to watch the recording | Click here to review the presentation
Mobilization (April 28 – May 2, 2025)
Before construction begins, the contractor will spend about a week mobilizing. This includes delivering equipment, setting up the work zone, marking utilities, and preparing for the removal of sidewalks and ramps.
Project Information Session
Join us to learn about the project’s goals to improve intersections and sidewalks to meet ADA requirements. We’ll share the project timeline, explain how we’re working to reduce impacts on pedestrians and businesses, and answer any questions you may have.
- Project Information Session | Thursday, May 8, 2025 | Add to Calendar | Join the Zoom
Pine Street (May 5 – June 17, 2025)
Work officially begins at the intersection of Colorado and Pine Street. Crews will remove and replace concrete ramps, sidewalks, and curbs to bring this area into compliance with ADA standards. Traffic and pedestrian detours may be in place during this time.
Fir Street (May 23 – June 17, 2025)
While construction wraps up at Pine Street, crews will begin work at the Fir Street intersection. These two work areas will overlap slightly, with coordination in place to limit disruption to nearby businesses and foot traffic.
Spruce Mid-Block (June 10 – June 30, 2025)
Between Pine and Willow, a mid-block crossing near Spruce Street will be improved with updated ramps and sidewalk surfaces. Work here will occur while Fir Street is nearing completion.
Willow Street (June 20 – July 18, 2025)
Construction moves westward to Willow Street. This area will receive the same accessibility upgrades, and pedestrian detours will help maintain access to businesses.
Alder Street (July 11 – August 15, 2025)
Alder Street marks the last intersection in Phase I of the project. By this point, work on all intersections between Pine and Alder (except for mid-block Spruce) will be completed or nearly complete.
Aspen Street (July 30 – August 22, 2025)
Phase II begins at the eastern end of the project area with improvements to the Aspen Street intersection. Construction activity continues to be phased to limit closures to one intersection at a time.