September 29 2024

Noise Variance Granted | 10 am to 5 pm

To ensure the Voodoo Employee Rental Housing Project wraps in time for move-in, the Town Manager of the Town of Telluride has granted a noise variance to allow for construction noise on Sunday, September 22, and Sunday, September 29 from 10 am to 5 pm.

September 22 2024

Noise Variance Granted | 10 am to 5 pm

To ensure the Voodoo Employee Rental Housing Project wraps in time for move-in, the Town Manager of the Town of Telluride has granted a noise variance to allow for construction noise on Sunday, September 22, and Sunday, September 29 from 10 am to 5 pm.

August 16 2024

Voodoo Employee Rental Housing Applications Close at Noon

July 24 2024

Voodoo Employee Rental Housing Lottery Applications Open

June 18 2024

Voodoo RFP Mandatory Meeting

May 06 2024

Voodoo Commercial Site Walk & Forum

Per Town Council’s direction, Town of Telluride staff will introduce a discussion regarding the commercial space at the Voodoo Affordable Housing Project at the Tuesday, May 14 regular meeting. The Town will host a public forum to gather feedback surrounding the desired use and selection process for the Voodoo commercial space on Monday, May 6, at 9 a.m. 

In December 2022, the Telluride Town Council and Telluride Housing Authority authorized the construction of the Voodoo Affordable Housing Project, which, in addition to 27 housing units, includes approximately 3700 gross square feet of tenant-finish commercial space, including walls and bathrooms. The spaces are located on the ground floor of the building along the Willow St. and Pacific Ave. frontages and within the historic contributing-rated shed. 

These commercial spaces are not “deed-restricted” to specific uses and would be suitable for office and retail activities for public, non-profit, or private tenants. The commercial spaces are not designed to support full restaurant, commercial kitchen, assembly, or childcare. Since the project's authorization, the historic shed portion of the commercial space has been designated for a regional Youth Hangout. The tenant-finished commercial space is slated for completion in September 2024.

Click here to listen to the public forum portion of the meeting.

April 29 2024

Historic Shed Returns to Construction Site

December 20 2023

Noise Variance

The Town of Telluride has granted a single-day noise variance for an extensive concrete pour at the Voodoo Project on Wednesday, December 20, 2023, from 5:00 am to 8:00 pm. 

This will be the second final concrete deck at the Voodoo Project and nearly identical to the first, just about 100 sqft larger.

The day’s itinerary is expected to go as follows:

  • 5 am – Pump truck arrival and setup.
  • 6 am – Concrete deliveries and pours begin. 
  • Noon – Concrete pouring concludes, finishing will proceed until completion.
September 18 → September 29 2023

Pacific Ave Closed Intermittently between Spruce and Willow

he Town of Telluride and Shaw Construction will close Pacific Avenue from Spruce to Willow intermittently beginning Monday, September 18. For the safety of the public, no parking, limited through traffic, and occasional full street closures should be expected on Pacific from Spruce to Willow for about two weeks. The road closures are expected to end on Friday, September 29.

August → October 2023

Structural Steel & Framing

May 29 2023

Excavation Expected to Begin

Excavation of the Voodoo work site is expected to begin as soon as pile driving concludes which, if all goes according to plan, should be the week of May 29th.

May 22 → May 24 2023

Noise Variance Granted (8 am to 6 pm)

The Town Manager has granted a noise variance for the project to allow for pile driving to occur from 8 am to 6 pm to expedite the project and wrap pile driving sooner than projected.

March 20 → June 06 2023

Pile Driving

The VooDoo Project is underway and will begin the loudest phase of construction on Monday, March 20 at 9 am. This phase includes driving large metal piles that will serve as foundational support for the future building. This phase of construction is expected to last about eight weeks. 

The Town of Telluride noise ordinance will be strictly followed with machine and construction noise occurring only from 9 am to 5 pm Monday through Friday.

March 27 2023

Final Demolition Work Begins

The final demolition work for the project is expected to commence the week of March 27 and will be completed in about 2 weeks’ time. 

The Town of Telluride noise ordinance will be strictly followed with machine and construction noise occurring only from 9 am to 5 pm Monday through Friday. 

The north sidewalk and some of the adjacent street on Pacific between Spruce and Willow will be closed for underground utility work associated with the project from March 27 through March 31.


February 10 2023

Historic Shed Relocated

The historic shed was temporarily relocated while construction is underway and will be reincorporated into the new build as a part of the structure and new facade. 

February 2023

Demolition and Site Preparation Work Begins

Demolition, site preparation, and rough grading begin in February of 2022 to occur throughout February and March.

December 2022

VooDoo Affordable Housing Project Authorized for Construction